G99 vs G100: When Export Limitation Saves Your Solar Project

Why G100 export limitation is the most under-used tool in UK commercial solar — and how it can save you 12 months and £180,000 in grid reinforcement.

Aerial view of a completed KMM commercial install, Market Deeping
Technical
Updated 2026-04-127 min readReviewed by Steve Moran

The grid is full. So what?

A third of the commercial G99 applications we submit in 2026 come back from the DNO with a "no capacity, reinforcement quote attached" letter. The reinforcement quotes range from £15,000 to £450,000. The reinforcement timelines range from 6 weeks to 24 months. For most businesses, neither the cost nor the timeline is acceptable.

G100 export limitation is the alternative: design the system to limit exports below the available grid threshold (often 0kW), and the DNO will approve the install without reinforcement, in a routine G99 timeline.

The trade-off

Export limitation costs you the SEG revenue you would have earned on exported kWh. For a typical UK commercial site with 70%+ self-consumption, that loss is around 4–6% of total system output — economically immaterial against the cost and time saved.

When G100 doesn't work

For sites with low daytime self-consumption (weekday-empty schools and offices in summer, retail with significant Sunday closure, agricultural sites with seasonal load), G100 export limitation can curtail 15–25% of output. At that level, the maths starts pointing toward either a battery to absorb the export, or paying the reinforcement contribution to unlock the grid.

The decision belongs in the spreadsheet, not the brochure. We model both cases for every site.

Request a Fully Funded Electrical & Structural Survey

Tell us about your roof, your bills and your goals. KMM runs a fully funded electrical & structural survey, designs a system, runs the numbers and tells you honestly whether solar makes sense for you. No deposit, no pressure.

Fully Funded Survey → 0115 647 3822
KMM bee Fully Funded Electrical & Structural Survey →