DNO Application Timelines in 2026: What to Actually Expect

How long G98, G99 and G100 applications take with each UK DNO in 2026, and what predicts a fast versus slow application.

Ground-mount solar install by KMM near Bath
Technical
Updated 2026-04-087 min readReviewed by Steve Moran

DNO turnaround in 2026 (typical, by region)

DNOG98 (28-day)G99 sub-50kVAG99 50-250kVAG99 250kVA-1MVA
NGED (formerly Western Power Distribution)28 days fast-track6-8 weeks8-12 weeks12-16 weeks
NGED (South West)28 days fast-track8-12 weeks10-16 weeks14-22 weeks
Northern Powergrid28 days fast-track6-10 weeks8-14 weeks14-20 weeks
UK Power Networks (E&SE)28 days fast-track10-16 weeks16-26 weeks26-52 weeks
Electricity North West28 days fast-track6-10 weeks10-14 weeks14-22 weeks
Scottish Power Energy Networks28 days fast-track10-14 weeks14-22 weeks22-32 weeks

What predicts a fast application

  • Modern industrial estates with dedicated infrastructure (iPort, Pride Park, i54, Cambridge Science Park) — designed with G99 headroom
  • Rural sites with under-used 11kV feeders — most of rural Lincolnshire and Nottinghamshire still has capacity
  • Sub-50kVA applications on any network — almost always fast-track
  • G100 export-limited designs — DNO has no objection because nothing exports beyond import capacity

What predicts a slow application

  • UK Power Networks territory — South East England congestion is the worst in the UK in 2026
  • M4 data centre corridor — practically full
  • Above 1MVA with no reinforcement contribution offered
  • Voltage-constrained rural feeders at end of long lines

How KMM speeds it up

We submit DNO applications week 1 of every project, in parallel with planning and design work — not at the end. We also know which contacts at each DNO accelerate review (most have informal "fast-lane" engineers who handle clean applications). For complex projects we engage the DNO at pre-application stage to flag the project before paperwork arrives. Our grid connection consultancy runs these applications for every KMM project.

Get your DNO application started

We prepare and submit G98, G99 and G100 applications as part of every KMM project.

Responds in <2 hrs

Or
What happens next
  1. We respond to every enquiry 9-5, Monday to Friday.
  2. Free drone survey + structural assessment booked at your convenience — zero ladder access.
  3. A bespoke, bound-in proposal with payback maths, finance routes and the grant landscape mapped for your site.

Request a Fully Funded Electrical & Structural Survey

Tell us about your roof, your bills and your goals. KMM runs a fully funded electrical & structural survey, designs a system, runs the numbers and tells you honestly whether solar makes sense for you. No deposit, no pressure.

Fully Funded Survey → Call 0115 647 3822
Connection timelines are also being reshaped by the national queue reform, and this explainer on DNO grid connection delays in 2026 covers how Gate 2 affects commercial solar projects.