DNO Application Timelines in 2026: What to Actually Expect

How long G98, G99 and G100 applications take with each UK DNO in 2026, and what predicts a fast versus slow application.

Ground-mount solar install by KMM near Bath
Technical
Updated 2026-04-087 min readReviewed by Steve Moran

DNO turnaround in 2026 (typical, by region)

DNOG98 (28-day)G99 sub-50kVAG99 50-250kVAG99 250kVA-1MVA
NGED (formerly Western Power Distribution)28 days fast-track6-8 weeks8-12 weeks12-16 weeks
NGED (United Kingdom / SW)28 days fast-track8-12 weeks10-16 weeks14-22 weeks
Northern Powergrid28 days fast-track6-10 weeks8-14 weeks14-20 weeks
UK Power Networks (E&SE)28 days fast-track10-16 weeks16-26 weeks26-52 weeks
Electricity North West28 days fast-track6-10 weeks10-14 weeks14-22 weeks
Scottish Power Energy Networks28 days fast-track10-14 weeks14-22 weeks22-32 weeks

What predicts a fast application

  • Modern industrial estates with dedicated infrastructure (iPort, Pride Park, i54, Cambridge Science Park) — designed with G99 headroom
  • Rural sites with under-used 11kV feeders — most of rural Lincolnshire and Nottinghamshire still has capacity
  • Sub-50kVA applications on any network — almost always fast-track
  • G100 export-limited designs — DNO has no objection because nothing exports beyond import capacity

What predicts a slow application

  • UK Power Networks territory — South East England congestion is the worst in the UK in 2026
  • M4 data centre corridor — practically full
  • Above 1MVA with no reinforcement contribution offered
  • Voltage-constrained rural feeders at end of long lines

How KMM speeds it up

We submit DNO applications week 1 of every project, in parallel with planning and design work — not at the end. We also know which contacts at each DNO accelerate review (most have informal "fast-lane" engineers who handle clean applications). For complex projects we engage the DNO at pre-application stage to flag the project before paperwork arrives.

Request a Fully Funded Electrical & Structural Survey

Tell us about your roof, your bills and your goals. KMM runs a fully funded electrical & structural survey, designs a system, runs the numbers and tells you honestly whether solar makes sense for you. No deposit, no pressure.

Fully Funded Survey → 0115 647 3822
KMM bee Fully Funded Electrical & Structural Survey →